Capital Improvement Projects
Pines and Mission Intersection Improvement Project
• Construction of intersection improvements, including a dedicated right-turn lane on southbound Pines Rd. to westbound Mission Ave., two dedicated left-turn lanes on eastbound Mission Ave. to northbound Pines Rd., modifying traffic signal operations, stormwater dry well installation and catch basin improvements
• Anticipated construction dates: 04/15/24-08/01/24
• Most construction activities will take place at night to minimize traveler impacts; however, the current phase of work is during the day and is expected to last through May and early June
• Expect lane restrictions, reduced speeds, and traffic delays
• Westbound Mission Ave. is closed west of Pines Rd. and a detour route is provided
• Business access will remain open
• Project Contact: Glenn Ritter, Project Manager 509-720-5018
For more Information, please visit the City's webpage for the Pines and Mission Intersection Improvement Project.
Private Construction Work
N. Keller (Between E. Sanson Ave. & E. Wellesley Ave.)
• Gas installation
• Anticipated construction dates: 05/13/24
• Road closure, signs posted
• Project Contact: Eclipse Excavation 509-328-2832
S. Felts Rd. (Between 4th Ave. & 8th Ave.)
• Frontage Improvements
• Anticipated construction dates: 05/15/24-05/16/24
• Road closure, signs posted
• Project Contact: McKey Construction LLC 509-720-3029
Utility Work
E. Indiana Ave. (Between Barker Rd. & N. Greenacres Rd.)
• Gas install
• Anticipated construction dates: 05/16/24-05/17/24
• Single lane closure with signs posted; flaggers onsite to direct vehicles through the construction zone
• Project Contact: Avista - Dave Noel 509-378-4413
N Bannen Rd., E Sprague Ave. - Phase 46B
• Gas main replacement
• Anticipated construction dates: 05/13/24-05/17/24
• Work zone taper with possible one lane closure with flaggers depending on parking
• Project Contact: NPL - Ed Trzcinski 509-425-3135
N. Blake Rd., 13414 E. Sprague Ave. - Phase 32A
• Gas main replacement
• Anticipated construction dates: 05/13/24-05/17/24
• Work zone taper with possible one lane closure with flaggers depending on parking
• Project Contact: NPL - Ed Trzcinski 509-425-3135
S. Best Rd., E. Main Ave. - Phase 46B
• Gas main replacement
• Anticipated construction dates: 05/13/24-05/17/24
• Work zone taper with possible one lane closure with flaggers depending on parking
• Project Contact: NPL - Ed Trzcinski 509-425-3135
S. Best Rd., E. 2nd Ave. - Phase 32B
• Gas main replacement
• Anticipated construction dates: 05/13/24-05/17/24
• Work zone taper with possible one lane closure with flaggers depending on parking
• Project Contact: NPL - Ed Trzcinski 509-425-3135
N. Burns Rd., E. Valleyway Ave. - Phase 46B
• Gas main replacement
• Anticipated construction dates: 05/13/24-05/17/24
• Work zone taper with possible one lane closure with flaggers depending on parking
• Project Contact: NPL - Ed Trzcinski 509-425-3135
Road Maintenance
S. Bowdish Rd. (E. 12th Ave. to E. Sprague Ave.)
• ADA Ramp upgrades and stormwater work
• Anticipated construction dates: 04/15/24-05/31/24
• Single lane closure with flaggers to guide vehicles through the construction zone
• Project Contact: City of Spokane Valley - Shane Arlt 509-720-5002