Utility Work
N. Flora Rd., E. Wellesley Ave. - Phase 1
• Gas main replacement
• Anticipated construction dates: 04/08/24-04/12/24
• Road closure on Flora Rd., sidewalk closed 350 feet from Wellesley Ave. to the south. Detour signs posted.
• Project Contact: NPL - Ed Tracinski 509-425-3135
S. Pierce Rd., E. 9th Ave., E. 10th Ave.
• Gas main replacement
• Anticipated construction dates: 04/08/24-04/12/24
• Lane closures on 9th, 10th and Pierce Rd. flaggers to guide vehicles through the construction zone. Signs posted.
• Project Contact: NPL - Ed Tracinski 509-425-3135
E. Montgomery Ave., E. Montgomery Dr., N. Woodruff Rd.
• Gas main replacement
• Anticipated construction dates: 04/08/24-04/12/24
• Lane closure with flaggers and traffic control devices at 10102 E. Montgomery Ave. to guide vehicles through the construction zone
• Project Contact: NPL - Ed Tracinski 509-425-3135
S. Dishman Rd. and E. 8th Ave. - Phase 45
• Gas main replacement
• Anticipated construction dates: 04/08/24-04/12/24
• Single lane closure with flaggers at 812 S. Dishman Rd. to guide vehicles through the construction zone. Signs posted.
• Project Contact: NPL - Ed Tracinski 509-425-3135
E. Railroad Ave., E. Sharp Ave. - Phase 35
• Gas main replacement
• Anticipated construction dates: 04/08/24-04/12/24
• Single lane closure with flaggers at 5209 E. Railroad Ave. to guide vehicles through the construction zone. Signs posted.
• Project Contact: NPL - Ed Tracinski 509-425-3135
N. Fancher Rd., E. Sharp Ave. - Phase 26
• Gas main replacement
• Anticipated construction dates: 04/08/24-04/12/24
• Single lane closure with flaggers at 1103 N. Fancher Rd. to guide vehicles through the construction zone. Signs posted.
• Project Contact: NPL - Ed Tracinski 509-425-3135
729 S. Carnahan Rd.
• New power pole insets
• Anticipated construction dates: 04/10/24
• Single lane closure with flaggers to guide vehicles through the construction zone. Signs posted.
• Project Contact: Avista - Ellsworth 509-309-5104
13502 E. Rich Ave.
• Underground power line extension
• Anticipated construction dates: 04/09/24
• Shoulder closure. Signs posted.
• Project Contact: Avista - Todd Harmon 509-503-8094
Private Construction
18521 E. Indiana Ave.
• Water main tap and sewer connection
• Anticipated construction dates: 04/02/24-04/08/24
• Road closed to through traffic
• Project Contact: Jewell Excavating 509-927-9600