Capital Improvement Projects
Sullivan Rd. Improvement
- Reconstruction of S. Sullivan Rd. from E. Sprague Ave. to E. 8th Ave.
- Intermittent single lane closures to continue through mid November to address final construction activities.
- Traffic devices will direct traffic through work zone.
- Project Contact: Kelly Lynch (509) 720-5001
Broadway and Park Intersection Improvements
- Reconstructs the existing intersection with concrete pavement, replaces old signal system, storm water improvements and new sidewalk on the west side of Park Road.
- Anticipated construction dates: August 8th – November 2023
- One lane in each direction will be provided on Broadway.
- Park Road between Broadway Ave and Cataldo Ave will be closed to through traffic.
- Park Road between Valleyway Ave and Broadway Ave will be closed to through traffic.
- Traffic devices will direct traffic through work zone.
- Access will be provided for property owners within the closure.
- Businesses are open.
- Contractor’s Public Liaison: Tina Westby (509) 385-4830
- Project Contact: Rob Lochmiller (509) 720-5010
Private Construction
N. Keller (Between E. Crown and E. Wellesley)
• Sewer tie-in
• Anticipated construction dates: 11/06/23 - 11/9/23
• Road closed.. Signs posted.
• Project Contact: Eclipse Excavation LLC (509) 328-2832
E. Valleyway (Between N Conklin and N Sullivan)
• Utility work
• Anticipated construction dates: 11/6/23 - 11/10/23
• Road closed. Signs posted.
• Project Contact: Liberty Contracting & Devl LLC - Brian Holecek 509) 599-2348
Utility Work
N. Pines (Between E. Sinto and E. Nora)
• Pole replacement
• Anticipated construction dates: 11/09/23 - 11/10/23 - night work: 7:30pm - 6:00am
• Single lane. Flaggers on site. Signs posted.
• Project Contact: Avista - Luse (509) 795-9150
N. Bradley (Between E. Desmet and E. Cataldo)
• Transformer work
• Anticipated construction dates: 11/08/23
• Single lane. Flaggers on site. Signs posted.
• Project Contact: Avista - T Harmon (509) 503-8094
S. Willow (Between E. Sprague and E. Appleway)
• Gas maintenance repair
• Anticipated construction dates: 11/09/23
• Road closed.. Signs posted.
• Project Contact: Avista - Travis Ward (509) 218-0711
Additional Resources
City of Spokane Valley Road Closures
Spokane County Road and Weight Restrictions
WSDOT Construction Projects
WSDOT Commercial Vehicle Services - Restrictions
National Weather Forecast - Spokane Valley
Eastern Washington Travel Alerts