Capital Improvement Projects
Sullivan Rd. Improvement
- Reconstruction of S. Sullivan Rd. from E. Sprague Ave. to E. 8th Ave.
- Intermittent single lane closures to continue through mid November to address final construction activities.
- Traffic devices will direct traffic through work zone.
- Project Contact: Kelly Lynch (509) 720-5001
Barker Rd at Union Pacific Railroad Crossing - Phase 2
- This paving project widens Euclid Ave and Barker Rd at the crossing of Union Pacific Railroad (UPRR).
- The project includes the addition of turn lanes; water, sewer, & stormwater utilities; a sidewalk on Euclid Ave.; and completion of the multi-use trail on Barker Road north of Euclid Ave to Trent.
- This final phase of the Barker Rd widening project requires coordination with the UPRR to replace the railroad tracks and crossing equipment.
- Anticipated construction dates: July 17th – October 2023
- Barker Road will be closed to through traffic for the duration of the project at the intersection of Euclid Ave in the vicinity of the Union Pacific Railroad; and Euclid Avenue will be closed between Barker Rd and Harmony Rd.
- Traffic devices will detour traffic around the work zone.
- Access will remain open for local access.
- During construction of the multi-use trail on Barker Road north of Euclid Ave to Trent, traffic control for a lane shift will be utilized to direct traffic through work zone.
- Contractor’s Public Liaison: Elyse Shattuck (208) 449-3377
- Project Contact: Kristen Armstrong (509) 720-5070
Broadway and Park Intersection Improvements
- Reconstructs the existing intersection with concrete pavement, replaces old signal system, storm water improvements and new sidewalk on the west side of Park Road.
- Anticipated construction dates: August 8th – October 2023
- One lane in each direction will be provided on Broadway.
- Park Road between Broadway Ave and Cataldo Ave will be closed to through traffic.
- Park Road between Valleyway Ave and Broadway Ave will be closed to through traffic.
- Traffic devices will direct traffic through work zone.
- Access will be provided for property owners within the closure.
- Businesses are open.
- Contractor’s Public Liaison: Tina Westby (509) 385-4830
- Project Contact: Rob Lochmiller (509) 720-5010
Argonne/Montgomery Intersection Improvements
- Punch List work from Argonne/Montgomery Intersection Improvements
- Anticipated construction date: 10/27/23
- Lane Restrictions anticipated on Montgomery East of Argonne
- Expect Delays
- Project Contact: Erica Amsden (509) 720-5012
- Contractor Public Liaison: Elyse Shattuck (208) 449-3377
Utility Work
E. Wellesley (Between N Evergreen and N Best)
• Pole inset
• Anticipated construction dates: 11/01/23
• Single lane. Flaggers on site. Signs posted.
• Project Contact: Avista - Luse (509) 795-9150
S. Bowdish / E 18th Ave.
• Install gas service
• Anticipated construction dates: 11/02/23
• Single lane. Flaggers on site. Signs posted.
• Project Contact: Avista - Trevor Butler (509) 276-0402
Additional Resources
City of Spokane Valley Road Closures
Spokane County Road and Weight Restrictions
WSDOT Construction Projects
WSDOT Commercial Vehicle Services - Restrictions
National Weather Forecast - Spokane Valley