06/25/23 - 07/01/23

Anticipated dates/times: Road maintenance projects are subject to change due to weather conditions and other unforeseen circumstances.


Capital Improvement Projects

Sullivan Rd. Improvement

  • Reconstruction of S. Sullivan Rd. from E. Sprague Ave. to E. 8th Ave.
  • Anticipated construction dates: 05/22/23 – October 2023
  • Right turns only from 4th East of Sullivan; No turns from 4th West of Sullivan; No through traffic on 4th at Sullivan.
  • Traffic devices will direct traffic through work zone.
  • Project Contact: Kelly Lynch (509) 720-5001
  • Contractor Public Liaison: Jamie Pannell (208) 966-0444

 

Park Rd. Sidewalk Project

  • Sidewalk construction between Nora Ave. and Baldwin Ave. 
  • Anticipated construction dates: 06/12/23 – July 2023
  • Baldwin Ave. will be closed at Park Rd.
  • Traffic devices will direct traffic through work zone.
  • Project Contact: Jeremiah Schreindl (509) 720-5020
  • Contractor Public Liaison: Brian Schmimmels (509) 991-6397)

 

Broadway Ave. Preservation

  • Pavement preservation project that grinds and overlays Broadway Ave from Fancher Rd. to Thierman Rd.
  • Anticipated construction dates: June 19th – July 2023 
  • One lane in each direction will be provided on Broadway for the duration of the project. 
  • Traffic devices will direct traffic through work zone.
  • Access to businesses are open.
  • Contractor’s Public Liaison: Dane Anderson (509)319-5113
  • Project Contact: Mitch Youngs (509) 720-5011

 

8th Ave Improvement

  • Repaving, Stormwater, sidewalk upgrades between Carnahan and Park Rd
  • New Sidewalk on north side of 8th between Thierman and Park
  • Anticipated construction dates: 06/20/23 – September 2023
  • 8th Ave closed between Thierman and Park 
  • Intermittent Flagging on 8th Ave between Carnahan and Thierman 
  • Project Contact: Kelly Lynch (509) 720-5001
  • Contractor Public Liaison: Kathleen Herzog (509) 828-0814

Utility Work

E 4th & S. Fancher
• Gas main work
• Anticipated construction dates: 6/29/23
• Single lane closure.  Flaggers on site
• Project Contact: CJ Leonard (509) 795-4096

E 4th & University
• Panel removal and replacement
• Anticipated construction dates: 6/28/23 - 6/29/23
• Lane shifts.  Signal will be in flash.
• Project Contact: Cameron-Reilly LLC (509) 466-555


Additional Resources

City of Spokane Valley Road Closures
Spokane County Road and Weight Restrictions
WSDOT Construction Projects
WSDOT Commercial Vehicle Services - Restrictions
National Weather Forecast - Spokane Valley
Eastern Washington Travel Alerts

City of Spokane Valley

10210 E. Sprague Avenue
Spokane Valley, WA  99206
www.spokanevalleywa.gov
(509) 720-5000

Share on Facebook
Share on Twitter
Share via Email

Copyright 2023 by City of Spokane Valley. All Rights Reserved.
10210 E. Sprague Avenue, Spokane Valley, WA 99206

Powered by
CivicSend - A product of CivicPlus